Summer's roadwork blitz: see list here

If you're hitting the roads for vacation this summer, it's time to plan your trip well in advance. The Swedish Transport Administration (Trafikverket) has provided a list of all the roadworks, road closures, detours, and stretches where the speed will be reduced.

The Swedish Transport Administration (Trafikverket) has released details about all planned road works in Skellefteå and the surrounding region during the summer of 2023.

The Swedish Transport Administration (Trafikverket) has released details about all planned road works in Skellefteå and the surrounding region during the summer of 2023.

Foto: Magnus Grimstedt

Skellefteå2023-05-19 12:28

There's a significant number of roads in the county being spruced up this summer, and in light of this, the Swedish Transport Administration (Trakifverket) has released information on the routes and stretches that will be impacted by roadworks.

–There is a great need for maintenance on our roads. It always feels rewarding when we can carry out tasks that will genuinely make a difference, says Christian Eriksson, head of road maintenance at the Swedish Transport Administration.

Some of the planned work has already begun, but the majority will commence in June, July, or August.

– Maintain your speed and drive carefully at roadwork sites. This enhances safety for you, your fellow road users, and those working on the roads, says Eriksson.

Roadworks on E4 in Västerbotten and Norrbotten:

E4, Sikeå-Gumboda

Work: Installing new surfacing, median barriers, wildlife fencing, and signage to create a dual carriageway. Traffic Impact: Narrowed lanes, reduced speed, traffic lights, temporary bypasses, and detours. Duration: May to November. Length: 10 km.

E4, Sikeå

Work: Construction of a new interchange. Traffic Impact: E4 traffic will be diverted to the ramps alongside the road while a new bridge is being built over E4. New temporary exits and entrances from Robertsfors and Sikeå harbor. Reduced speeds. Duration: Starting from June 2023, completion in 2024. Length: 1.6 km.

E4, Lillåbron-Sävar

Work: Installation of side barriers. Traffic Impact: One lane closed, oncoming traffic. Duration: Mid-May to Mid-June.

E4, Umeå-Nordmaling

Work: Installation of side barriers. Traffic Impact: One lane closed, oncoming traffic. Duration: Mid-May to Mid-June.

E4, Nordmaling-Husum

Work: Installation of wildlife fencing. Traffic Impact: Minor temporary diversions may occur in the construction area. Duration: May to June.

E12, Holmsund-Obbola-Umeå

Work: Replacement of waterproofing and resurfacing on the bridge over Ume River (Obbolabron). Traffic Impact: One lane closed, traffic lights. Duration: May to August. Length: 390 meters.

E12, Western Link, Umeå Project, Ume River-E4

Work: New construction of the Western Link project connecting E12 and Ume River with E4. Traffic Impact: Minor temporary diversions may occur in the construction area. Duration: May to October.

E4, Skellefteå-Ostvik Interchange

Work: Resurfacing work. Traffic Impact: Traffic diversions and traffic lights. Duration: June to August. Length: 17.4 km.

E4, Daglösten-Bureå

Work: Resurfacing. Traffic Impact: Traffic diversions and traffic lights. Duration: June to August. Length: 16 km.

Road 364, between the intersection with Road 774 and approximately 3 km south to Långviken

Work: Completion of roadside work. Traffic Impact: One lane closed, oncoming traffic. Duration: May to September. Length: 2 km.

Road 365, Kvarnåsen-Norsjövallen

Work: Resurfacing work. Traffic Impact: Traffic diversions and traffic lights. Duration: June to August. Length: 15.4 km.

Road 372 and 827, Skelleftehamn

Work: New bridge over Road 827. Traffic Impact: Reduced speed, narrow passage. Duration: May to August. Length: 0.8 km.

Road 372, Skellefteå-Skelleftehamn

Work: Resurfacing work. Traffic Impact: Night work from 18:00 to 06:00. Traffic diversions guided by flaggers or traffic lights. Duration: May to August. Length: 17.5 km.

Road 774, Skellefteå Airport-Orrbäcken

Work: Strengthening, load-bearing measures, clearing of roadside areas, new lighting. Traffic Impact: One lane closed, oncoming traffic, detours. Duration: May to October. Length: 8 km.